Dear Islanders,
The Road Commission has embarked on our 2018 project this week. We will be tying in to two areas where we received a drainage agreement for two existing outlets to the lake. A big thank you goes out to the Castele and Portik families for making this possible. Thank you for the signed Drainage Agreements!
 

 

  • The Castele drainage portion of the work extends from 3790 to 3884 Memorial Shoreway.
  • The Portik drainage portion of the work extends from 4134 to 4246 Memorial Shoreway

 

 
We will be installing underground drainage the next few weeks followed by removal of asphalt in the work areas the week after the infamous garage sale.
The contractors are committed to keeping the roads passable and most of the work will occur between Monday and Thursday . Estimated completion is scheduled before Labor Day weekend.
Please don’t hesitate to call or e-mail Rick Schulz if you have any questions or concerns.